LodeHQ
AI news for people who shipFree, by email

AI · a16z.com · Friday, 9 October 2026

Texas freezes data center permits as its power queue hits 474 GW

Texas has frozen new data center permits after ERCOT’s large-customer queue jumped from 63 GW at the end of 2024 to 474 GW by June, with data centers making up about 90% of it. Developers often submit speculative projects across multiple sites, leaving planners unable to tell which loads are real or who should pay for upgrades. Local trust is also weak: only 28 of 377 companies answered a state survey on resource use.

Read the source: a16z.com ↗In the 9 October issue →